News - ThoYu Realizes Plastic Pallet Production Line in Thailand From Assembly to Mass Production in 15 Days
case banner

ThoYu Realizes Plastic Pallet Production Line in Thailand From Assembly to Mass Production in 15 Days

In Thailand’s scorching March heat, with workshop temperatures nearing 40°C, how long does it take to assemble, debug, and put into operation a complete compression molding production line?

ThoYu’s answer: 15 days.

bannerT

(The production line in Thailand was successfully delivered)

IMG_0318.HEIC

(group photo)

Finished Products Meet All Standards

Despite extreme heat and humidity, the custom plastic pallet production line in Thailand was successfully commissioned and has now entered mass production:

  • Smooth surface, uniform specifications
  • Dynamic load: 1.5 tons | Static load: 6 tons
  • Supports direct waste plastic recycling – no complicated granulation needed

PALLET

(Finished product pallet display)

Why Did a 40-Year Thai Plastics Leader Choose ThoYu?

The client is a benchmark enterprise in Thailand’s plastics industry: 40 years of experience, operating three wholly-owned companies. Factory equipped with 40 pallet machines and 20 granulators. Holds a significant market share in plastic pallet production in Thailand and across Southeast Asia

As virgin plastic costs continue to rise, waste plastic recycling has become a key way to reduce costs. Traditional manual injection molding machines cannot efficiently process waste materials.

ThoYu’s compression molding plastic pallet production line eliminates the need for granulation, directly converting waste plastic into high-quality pallets – significantly lowering raw material costs.

plastic-pallet-equipment

plastic pallet machine

PLC

(PLC)

From July to August last year, ThoYu’s technical team traveled between China and Thailand multiple times, tailoring a waste plastic regeneration solution based on the client’s specific material characteristics.

15-Day Installation Timeline: Execution Every Single Day

In Thailand’s 40°C workshop environment, Senior Engineer Mr. Zhang led the team with precision and efficiency:

(The machine installation is in progress…

Day 1: Arrived at Bangkok airport at 12:20 PM; began equipment verification and installation planning in the afternoon

Days 2–3: Completed assembly of the core compression molding machine

Days 4–5: Assembled primary/secondary extruders and dosing tank

extruder

(extruder)

Days 6–7: Installed cable trays and wiring under 40°C heat

Days 8–11: Integrated chiller, robotic arm, conveyor belt – achieving full material flow

Days 12–13: Installed covers and debugged line coordination

Days 14–15: Provided two days of hands-on training (operation, troubleshooting, maintenance)

The line was handed over, ready for independent operation – no additional support needed.

A 15 - day delivery is not a coincidence. It results from ThoYu’s standardized, process - driven, and visual delivery system. There are real – time progress updates and issue feedback. ThoYu has close collaboration with the Thai client to overcome heat and schedule pressures.

 prioritizes customers by integrating cutting - edge technology, efficient execution, and attentive service to offer customized compression molding solutions for clients worldwide.

If you are also facing challenges due to the rising costs of plastic raw materials, contact TUOYU today to optimize your plastic pallet production in Thailand and globally.

 

Write your message here and send it to us

Post time: Apr-02-2026